NCS Fluid Systems Hydro-testing across Canada

NCS Fluid Handling Systems - Across Canada Leaders in tank Hydro-testing

NCS Fluid Handling Systems - Across Canada Leaders in tank Hydro-testing

NCS Fluid Handling Systems now Testing Tanks Across Canada as supplier of choice

Often misunderstood and confused with Water Transfer, Hydro-Testing is an important and needed element of completing the tank and tank base construction process.

Hydro-testing tanks takes expertise to properly ensure a tank is tested completely prior to service. 

Items such as:

Water analysis ensuring test water suitability and establishing baseline so when test water is returned it is cleaner than the original source analysis.

Temporary Diversion License (TDL) and water meters in place ensuring that the requested amount of water on the TDL is withdrawn and returned.

On our NCS projects we coordinate all crossing agreements which are binding contracts between NCS Fluid Handling Systems and stakeholders, utility companies and other agents that have services above or below ground and are non transferable and valid for a stated period of time. Crossing agreements are put in place ensuring all stakeholders have been consulted and have granted access for temporary test water supply lines to cross land and existing utilities.

A Water Filtration plan and system in place in when all tank hydro-testing is completed ensuring test water is all returned to source cleaner than originally withdrawn. Interesting note is that if test water was heated to prevent freezing during testing the water is cooled to source water temperature as it is released, preventing temperature shock to aquatic life or plants.

Fish screens on suction inlets ensuring that no aquatic life is affected.

API TANK Hydrotest

There are three main codes when it comes to the manufacturing of field erected storage tanks. When experienced crews are required to perform all services related to a fully operational and functional hydro testing North American customers’ look the NCS Fluid Handling Systems and the skilled team trained to perform all operational checks related to the full functional testing of these tanks, including hydrotest and stability of tank base.

While some water management businesses will advertise the filling of a tank or multiple tanks with water as performing the Hydro-static test, this only contributes to confusing what a fully functional test is. At NCS Fluid Handling Systems we understand the total cost of ownership of these valuable tank assets and the long-term expectations owners have for their continued performance, that is why NCS provides specialized training to all levels of the team, so that these dedicated specialists meet the specialized skills required and enhanced degree of service owners expect for pre-commissioning these value assets. Starting with temporary water diversion licensing, surveying crossing agreements, water analysis (pre-test and post test hydrotest water), water fill and transfer, full operational checks of floating roofs, stairs, ancillary components, filtration, iron removal, erosion controlled water release to source and tank dewatering and drying. As the sole source for any or these required services NCS Fluid Handling Systems understands our clients needs fully, not just one part of a valuable overall service.

API 650 STANDARD

American Petroleum Institute (API) 650 was originally released in 1961 and is the international standard for tanks widely used for tanks that are designed to internal pressures of 2.5 PSI or less and store products such as crude oil, gasoline, chemicals and produced water.

 API realized that the industry needed a designer specification that allowed for regional and global considerations that the API 12 series did not provide. The API-12C specification was, for lack of a better term “pre-engineered and tested” as most of the 12 series tanks are, they are standardized designs based on practical applications or predetermined size and performance parameters. So, from the foundation of API-12C the API-650 became the governing code for petroleum product storage tanks. This standard now provided designers the considerations for varying conditions that globally affect tank design, such as extreme weather variations and material performance, seismic design and zones, wind overturning, internal pressures, varying heights and diameters, material grades and thickness, non-destructive testing as well as hydro testing for all the above conditions and variations.

API 620 STANDARD

API 620 picks up where API-650 leaves off with regards to pressure and is the governing standard for the design and large, above ground field-assembled storage tanks that contain petroleum gases or vapors as well as other liquid products.  These storage tanks are designed to operate at 250°F or less with an operating pressure of up to 15 PSI, at which point the ASME codes take over for pressure vessel design. For the most part API 620 Tanks are typically referenced for Liquefied Natural Gas, Liquid Oxygen or other storage of chemicals which require internal design pressures more than those allowed by API 650.

The API-620 also allows for consideration of non-fully supported flat bottoms, or in simpler terms unsupported cones or bottom not fully supported reference API-620, as well may reference American Society of manufacturing Engineers (ASME) for compression sections (But this opens a whole other discussion).

 

API 620 also includes appendixes that cover additional requirements;

  • Appendix Q for low-pressure storage tanks for liquid hydrocarbon gases,
  • Appendix R for low-pressure storage tanks for refrigerated products,
  • Appendix S for austenitic stainless-steel tanks.

API 620 also covers requirements for examination methods, procedures, acceptance criteria, and qualification of examination personnel. API 620 examination requirements, but are not limited too, non-destructive examination (NDE) which include, visual examination (VT), magnetic particle testing (MP), liquid penetrant testing (LPT), radio-graphic testing (RT), ultrasonic testing (UT) and other applicable test methods may include vacuum box leak test, air-solution film leak test and Hydro static testing where the tank is filled with water similar to API-650 with the addition of a pneumatic pressure applied in accordance with all applicable quality and safety processes and procedures to the envelope above the shell to roof juncture. 

 API 12D STANDARD

Like the old API-12C specification the remaining tank specification is API 12D which is utilized for the construction and field erection of welded tanks for storage of production fluids. Typically, this standard is used by upstream petroleum producers or companies. Whereas welded shop fabricated tanks used in this same service are governed by the API 12 F standard, the API 12D standard is used for field erected tanks. API 12D does not have the designer latitudes that API-650 has and uses predetermined tank sizes, dimensions, internal design pressure or vacuum pressure (also known as in and out breathing), and set criteria for accessories and testing requirements.

As a point of interest, for a tank to be a certified API – 12F or 12 D tank the nameplate must bear the API Monogram.